SPT - Strategic Agreement for Transmission Overhead Line Works

SP TRANSMISSION PLC

Buyer Contact Info

Buyer Name: SP TRANSMISSION PLC

Buyer Address: 320 St. Vincent Street, Glasgow, UKM82, G2 5AD, United Kingdom

Contact Name: SPT Strategic Projects

Contact Email: OHLstrategicagreement@scottishpower.com

Status
complete
Procedure
selective
Value
600000000.0 GBP
Published
22 Aug 2025, 12:35
Deadline
n/a
Contract Start
n/a
Contract End
n/a
Category
works
CPV
45231400 - Construction work for electricity power lines
Region
n/a
Awarded To
Balfour Beatty Utility Solutions Limited, M Group Energy (Network Infrastructure) Limited, Morgan Sindall Construction & Infrastructure Ltd, Aureos Energy Limited, Wood Transmission And Distribution Limited, Painhas S.A., Power Lines, Pipes and Cables Limited, Cobra Instalaciones y Servicios SA
Official Source
Open Find a Tender

Description

SPT has appointed partners with the capacity and capability to deliver its strategic infrastructure priorities through a strategic collaborative delivery model. The agreement comprises three (3) Lots: - • Lot 1 is for 400kV Overhead Line Works involving a HTLS (High Temperature Low Sag) conductor system • Lot 2 is for 275kV and 400kV Overhead Line Works • Lot 3 is for 132kV Overhead Line Works The partners appointed to the agreement may be allocated projects and they will provide engineering and design, procure any materials and equipment, and carry out the construction works as per the agreed design with SPT. The contractual arrangements comprise a main Framework Agreement regulating the rights and obligations of SPT and the partners, with call-off contracts for individual packages using the NEC4 family of contracts. There is no guarantee, express or implied, that the appointed partners under the Framework Agreement will receive any, or a particular volume or value of work.

Linked Documents

No linked documents found for this notice.

Opportunity Context

Lots

Lot Title: Design & Construction of 400kV Overhead Lines with HTLS

Lot Description: Please refer to the contract notice that was published on 21 December 2023 with notice reference 2023/S 000-037752 (the Contract Notice).

Lot 1 Status: cancelled

Lot 1 Has Options: Yes

Lot 1 Options: The duration of the Framework Agreement is 5 years, but extendable up to 10 years (in aggregate) at SPT's option. The duration of call-off contracts for specific packages may extend beyond the end of the overarching Framework Agreement.

Lot 1 Award Criterion (quality): Non-Commercial

Lot 1 Award Criterion (cost): Commercial

Lot Title: Design & Construction of 275kV and 400kV Overhead Lines

Lot Description: Please refer to the contract notice that was published on 21 December 2023 with notice reference 2023/S 000-037752 (the Contract Notice)

Lot 2 Status: cancelled

Lot 2 Has Options: Yes

Lot 2 Options: The duration of the Framework Agreement is 5 years, but extendable up to 10 years (in aggregate) at SPT's option. The duration of call-off contracts for specific packages may extend beyond the end of the overarching Framework Agreement.

Lot 2 Award Criterion (quality): Non-Commercial

Lot 2 Award Criterion (cost): Commercial

Lot Title: Design & Construction of 132kV Overhead Line Works

Lot 3 Status: cancelled

Lot 3 Has Options: Yes

Lot 3 Options: The duration of the Framework Agreement is 5 years, but extendable up to 10 years (in aggregate) at SPT's option. The duration of call-off contracts for specific packages may extend beyond the end of the overarching Framework Agreement.

Lot 3 Award Criterion (quality): Non-Commercial

Lot 3 Award Criterion (cost): Commercial

Contracts

Contract Title: Design & Construction of 400kV Overhead Lines with HTLS

Contract Title: Design & Construction of 275kV and 400kV Overhead Lines

Contract Title: Design & Construction of 132kV Overhead Line Works

Awards

Award Title: Design & Construction of 400kV Overhead Lines with HTLS

Award Title: Design & Construction of 275kV and 400kV Overhead Lines

Award Title: Design & Construction of 132kV Overhead Line Works

Raw Notice JSON

Expand raw payload
{
  "awards": [
    {
      "id": "050887-2025-1",
      "relatedLots": [
        "1"
      ],
      "status": "active",
      "suppliers": [
        {
          "id": "GB-COH-01062438",
          "name": "Balfour Beatty Utility Solutions Limited"
        },
        {
          "id": "GB-COH-00245626",
          "name": "M Group Energy (Network Infrastructure) Limited"
        },
        {
          "id": "GB-COH-04273754",
          "name": "Morgan Sindall Construction \u0026 Infrastructure Ltd"
        }
      ],
      "title": "Design \u0026 Construction of 400kV Overhead Lines with HTLS"
    },
    {
      "id": "050887-2025-2",
      "relatedLots": [
        "2"
      ],
      "status": "active",
      "suppliers": [
        {
          "id": "GB-COH-01062438",
          "name": "Balfour Beatty Utility Solutions Limited"
        },
        {
          "id": "GB-COH-12930461",
          "name": "Aureos Energy Limited"
        },
        {
          "id": "GB-COH-04273754",
          "name": "Morgan Sindall Construction \u0026 Infrastructure Ltd"
        },
        {
          "id": "GB-COH-00245626",
          "name": "M Group Energy (Network Infrastructure) Limited"
        },
        {
          "id": "GB-COH-11829648",
          "name": "Wood Transmission And Distribution Limited"
        },
        {
          "id": "GB-FTS-158716",
          "name": "Painhas S.A."
        }
      ],
      "title": "Design \u0026 Construction of 275kV and 400kV Overhead Lines"
    },
    {
      "id": "050887-2025-3",
      "relatedLots": [
        "3"
      ],
      "status": "active",
      "suppliers": [
        {
          "id": "GB-COH-01062438",
          "name": "Balfour Beatty Utility Solutions Limited"
        },
        {
          "id": "GB-COH-12930461",
          "name": "Aureos Energy Limited"
        },
        {
          "id": "GB-COH-04273754",
          "name": "Morgan Sindall Construction \u0026 Infrastructure Ltd"
        },
        {
          "id": "GB-COH-00245626",
          "name": "M Group Energy (Network Infrastructure) Limited"
        },
        {
          "id": "GB-COH-SC062782",
          "name": "Power Lines, Pipes and Cables Limited"
        },
        {
          "id": "GB-FTS-158716",
          "name": "Painhas S.A."
        },
        {
          "id": "GB-FTS-158717",
          "name": "Cobra Instalaciones y Servicios SA"
        },
        {
          "id": "GB-COH-11829648",
          "name": "Wood Transmission And Distribution Limited"
        }
      ],
      "title": "Design \u0026 Construction of 132kV Overhead Line Works"
    }
  ],
  "bids": {
    "statistics": [
      {
        "id": "1",
        "measure": "bids",
        "relatedLot": "1",
        "value": 3
      },
      {
        "id": "3",
        "measure": "bids",
        "relatedLot": "2",
        "value": 6
      },
      {
        "id": "5",
        "measure": "bids",
        "relatedLot": "3",
        "value": 8
      },
      {
        "id": "2",
        "measure": "electronicBids",
        "relatedLot": "1",
        "value": 3
      },
      {
        "id": "4",
        "measure": "electronicBids",
        "relatedLot": "2",
        "value": 6
      },
      {
        "id": "6",
        "measure": "electronicBids",
        "relatedLot": "3",
        "value": 8
      }
    ]
  },
  "buyer": {
    "id": "GB-COH-SC189126",
    "name": "SP TRANSMISSION PLC"
  },
  "contracts": [
    {
      "awardID": "050887-2025-1",
      "dateSigned": "2024-12-02T00:00:00Z",
      "id": "050887-2025-1",
      "status": "active",
      "title": "Design \u0026 Construction of 400kV Overhead Lines with HTLS",
      "value": {
        "amount": 600000000,
        "currency": "GBP"
      }
    },
    {
      "awardID": "050887-2025-2",
      "dateSigned": "2024-12-02T00:00:00Z",
      "id": "050887-2025-2",
      "status": "active",
      "title": "Design \u0026 Construction of 275kV and 400kV Overhead Lines",
      "value": {
        "amount": 1875000000,
        "currency": "GBP"
      }
    },
    {
      "awardID": "050887-2025-3",
      "dateSigned": "2024-12-02T00:00:00Z",
      "id": "050887-2025-3",
      "status": "active",
      "title": "Design \u0026 Construction of 132kV Overhead Line Works",
      "value": {
        "amount": 525000000,
        "currency": "GBP"
      }
    }
  ],
  "date": "2025-08-22T13:35:04+01:00",
  "description": "All financial values stated in this notice are calculated using current prices plus assumed inflation based on RPI forecast rates to 2034. All values are estimates only and the final outturn values will depend on the precise works and services required to be delivered, the means of delivery, the way in which programme and project risks materialise, the actual rates of inflation up to completion of the programme, and other factors.\nThe precise details of each identified project, including specific location, route, form of electricity network infrastructure, construction methodology, and any associated mitigation or enhancement schemes are indicative and remain to be confirmed. The final project details are subject to all necessary consents being obtained (such as any required DCO, Electricity Act 1989 consent or planning permission), the requirements of those consents, and the terms of any necessary land rights to be secured to enable project delivery. SPT gives no commitment as to the basis on which any necessary consents or land rights will be applied for, or obtained.\nThis Framework Agreement, along with other framework agreements that SPT may procure through separate procurement processes, will contribute to SPT\u0027s delivery of its strategic projects under the Holistic Network Design (HND) model (which are funded by the Accelerated Strategic Transmission Investment, Large Onshore Transmission Investment and Medium Sized Investment Project frameworks) as well as any baseline projects forming part of SPT\u0027s RIIO-T2 and RIIO-T/3 price control settlements and any customer connection projects that SPT considers appropriate to be delivered under this model. For the avoidance of doubt, SPT may have separate arrangements for the delivery of similar works to the works which SPT intends to procure under the Framework Agreement but such arrangements may be based on a different delivery model.\nIt is currently anticipated that SPT\u0027s HND programme will be delivered by the partners through these Framework Agreements and the call-off contracts awarded under them, and the full scope of that is included in the scope advertised by this notice.\nHowever, and without limiting that, the works and services awarded to the partners through this Framework Agreement, and the other framework agreements, may extend beyond work required for the HND programme to involve additional works and services, through the award of further contracts in reliance on the procedure in Regulation 48(4)(e) of the Utilities Contracts (Scotland) Regulations 2016 concerning direct awards for new works, services or both, consisting of the repetition of similar works or services. Any contracts for new works or services consisting of the repetition of similar works or services will (as relevant in the circumstances) conform to the requirements of SPT\u0027s HND programme and / or for a particular project for which contracts are called-off under these Framework Agreements",
  "id": "050887-2025",
  "initiationType": "tender",
  "language": "en",
  "ocid": "ocds-h6vhtk-04295b",
  "parties": [
    {
      "address": {
        "countryName": "United Kingdom",
        "locality": "Glasgow",
        "postalCode": "G2 5AD",
        "region": "UKM82",
        "streetAddress": "320 St. Vincent Street"
      },
      "contactPoint": {
        "email": "OHLstrategicagreement@scottishpower.com",
        "name": "SPT Strategic Projects"
      },
      "details": {
        "classifications": [
          {
            "description": "Electricity",
            "id": "ELECTRICITY",
            "scheme": "TED_CE_ACTIVITY"
          }
        ],
        "url": "http://www.spenergynetworks.co.uk/"
      },
      "id": "GB-COH-SC189126",
      "identifier": {
        "id": "SC189126",
        "legalName": "SP TRANSMISSION PLC",
        "scheme": "GB-COH"
      },
      "name": "SP TRANSMISSION PLC",
      "roles": [
        "buyer"
      ]
    },
    {
      "address": {
        "countryName": "United Kingdom",
        "locality": "Glasgow",
        "region": "UK"
      },
      "details": {
        "scale": "large"
      },
      "id": "GB-COH-01062438",
      "identifier": {
        "id": "01062438",
        "legalName": "Balfour Beatty Utility Solutions Limited",
        "scheme": "GB-COH"
      },
      "name": "Balfour Beatty Utility Solutions Limited",
      "roles": [
        "supplier"
      ]
    },
    {
      "address": {
        "countryName": "United Kingdom",
        "locality": "London",
        "region": "UK"
      },
      "details": {
        "scale": "large"
      },
      "id": "GB-COH-01062438",
      "identifier": {
        "id": "01062438",
        "legalName": "Balfour Beatty Utility Solutions Limited",
        "scheme": "GB-COH"
      },
      "name": "Balfour Beatty Utility Solutions Limited",
      "roles": [
        "supplier"
      ]
    },
    {
      "address": {
        "countryName": "United Kingdom",
        "locality": "Stevenage",
        "region": "UK"
      },
      "details": {
        "scale": "large"
      },
      "id": "GB-COH-00245626",
      "identifier": {
        "id": "00245626",
        "legalName": "M Group Energy (Network Infrastructure) Limited",
        "scheme": "GB-COH"
      },
      "name": "M Group Energy (Network Infrastructure) Limited",
      "roles": [
        "supplier"
      ]
    },
    {
      "address": {
        "countryName": "United Kingdom",
        "locality": "London",
        "region": "UK"
      },
      "details": {
        "scale": "large"
      },
      "id": "GB-COH-04273754",
      "identifier": {
        "id": "04273754",
        "legalName": "Morgan Sindall Construction \u0026 Infrastructure Ltd",
        "scheme": "GB-COH"
      },
      "name": "Morgan Sindall Construction \u0026 Infrastructure Ltd",
      "roles": [
        "supplier"
      ]
    },
    {
      "address": {
        "countryName": "United Kingdom",
        "locality": "London",
        "region": "UK"
      },
      "details": {
        "scale": "large"
      },
      "id": "GB-COH-12930461",
      "identifier": {
        "id": "12930461",
        "legalName": "Aureos Energy Limited",
        "scheme": "GB-COH"
      },
      "name": "Aureos Energy Limited",
      "roles": [
        "supplier"
      ]
    },
    {
      "address": {
        "countryName": "United Kingdom",
        "locality": "Knutsford",
        "region": "UK"
      },
      "details": {
        "scale": "large"
      },
      "id": "GB-COH-11829648",
      "identifier": {
        "id": "11829648",
        "legalName": "Wood Transmission And Distribution Limited",
        "scheme": "GB-COH"
      },
      "name": "Wood Transmission And Distribution Limited",
      "roles": [
        "supplier"
      ]
    },
    {
      "address": {
        "countryName": "Portugal",
        "locality": "Viana do Castelo",
        "region": "PT"
      },
      "details": {
        "scale": "large"
      },
      "id": "GB-FTS-158716",
      "identifier": {
        "legalName": "Painhas S.A.",
        "noIdentifierRationale": "notOnAnyRegister"
      },
      "name": "Painhas S.A.",
      "roles": [
        "supplier"
      ]
    },
    {
      "address": {
        "countryName": "United Kingdom",
        "locality": "Scotland",
        "region": "UKM"
      },
      "details": {
        "scale": "sme"
      },
      "id": "GB-COH-SC062782",
      "identifier": {
        "id": "SC062782",
        "legalName": "Power Lines, Pipes and Cables Limited",
        "scheme": "GB-COH"
      },
      "name": "Power Lines, Pipes and Cables Limited",
      "roles": [
        "supplier"
      ]
    },
    {
      "address": {
        "countryName": "Spain",
        "locality": "Madrid",
        "region": "ES"
      },
      "details": {
        "scale": "large"
      },
      "id": "GB-FTS-158717",
      "identifier": {
        "legalName": "Cobra Instalaciones y Servicios SA",
        "noIdentifierRationale": "notOnAnyRegister"
      },
      "name": "Cobra Instalaciones y Servicios SA",
      "roles": [
        "supplier"
      ]
    },
    {
      "address": {
        "countryName": "United Kingdom",
        "locality": "Glasgow",
        "postalCode": "G5 9DA",
        "streetAddress": "1 Carlton Place"
      },
      "id": "GB-FTS-2553",
      "identifier": {
        "legalName": "Glasgow Sheriff Court"
      },
      "name": "Glasgow Sheriff Court",
      "roles": [
        "reviewBody"
      ]
    }
  ],
  "tag": [
    "award",
    "contract"
  ],
  "tender": {
    "classification": {
      "description": "Construction work for electricity power lines",
      "id": "45231400",
      "scheme": "CPV"
    },
    "description": "SPT has appointed partners with the capacity and capability to deliver its strategic infrastructure priorities through a strategic collaborative delivery model. \nThe agreement comprises three (3) Lots: -\n\u2022 Lot 1 is for 400kV Overhead Line Works involving a HTLS (High Temperature Low Sag) conductor system \n\u2022 Lot 2 is for 275kV and 400kV Overhead Line Works\n\u2022 Lot 3 is for 132kV Overhead Line Works\nThe partners appointed to the agreement may be allocated projects and they will provide engineering and design, procure any materials and equipment, and carry out the construction works as per the agreed design with SPT.\nThe contractual arrangements comprise a main Framework Agreement regulating the rights and obligations of SPT and the partners, with call-off contracts for individual packages using the NEC4 family of contracts.\nThere is no guarantee, express or implied, that the appointed partners under the Framework Agreement will receive any, or a particular volume or value of work.",
    "id": "SPT-OHL-SA",
    "items": [
      {
        "additionalClassifications": [
          {
            "description": "Construction work for electricity power lines",
            "id": "45231400",
            "scheme": "CPV"
          }
        ],
        "deliveryAddresses": [
          {
            "region": "UKM"
          }
        ],
        "id": "1",
        "relatedLot": "1"
      },
      {
        "additionalClassifications": [
          {
            "description": "Construction work for electricity power lines",
            "id": "45231400",
            "scheme": "CPV"
          }
        ],
        "deliveryAddresses": [
          {
            "region": "UKM"
          }
        ],
        "id": "2",
        "relatedLot": "2"
      },
      {
        "additionalClassifications": [
          {
            "description": "Construction work for electricity power lines",
            "id": "45231400",
            "scheme": "CPV"
          }
        ],
        "deliveryAddresses": [
          {
            "region": "UKM"
          }
        ],
        "id": "3",
        "relatedLot": "3"
      }
    ],
    "legalBasis": {
      "id": "32014L0025",
      "scheme": "CELEX"
    },
    "lots": [
      {
        "awardCriteria": {
          "criteria": [
            {
              "description": "50%",
              "name": "Non-Commercial",
              "type": "quality"
            },
            {
              "description": "50%",
              "name": "Commercial",
              "type": "cost"
            }
          ]
        },
        "description": "Please refer to the contract notice that was published on 21 December 2023 with notice reference 2023/S 000-037752 (the Contract Notice).",
        "hasOptions": true,
        "id": "1",
        "options": {
          "description": "The duration of the Framework Agreement is 5 years, but extendable up to 10 years (in aggregate) at SPT\u0027s option. The duration of call-off contracts for specific packages may extend beyond the end of the overarching Framework Agreement."
        },
        "status": "cancelled",
        "title": "Design \u0026 Construction of 400kV Overhead Lines with HTLS"
      },
      {
        "awardCriteria": {
          "criteria": [
            {
              "description": "50%",
              "name": "Non-Commercial",
              "type": "quality"
            },
            {
              "description": "50%",
              "name": "Commercial",
              "type": "cost"
            }
          ]
        },
        "description": "Please refer to the contract notice that was published on 21 December 2023 with notice reference 2023/S 000-037752 (the Contract Notice)",
        "hasOptions": true,
        "id": "2",
        "options": {
          "description": "The duration of the Framework Agreement is 5 years, but extendable up to 10 years (in aggregate) at SPT\u0027s option. The duration of call-off contracts for specific packages may extend beyond the end of the overarching Framework Agreement."
        },
        "status": "cancelled",
        "title": "Design \u0026 Construction of 275kV and 400kV Overhead Lines"
      },
      {
        "awardCriteria": {
          "criteria": [
            {
              "description": "50%",
              "name": "Non-Commercial",
              "type": "quality"
            },
            {
              "description": "50%",
              "name": "Commercial",
              "type": "cost"
            }
          ]
        },
        "description": "Please refer to the contract notice that was published on 21 December 2023 with notice reference 2023/S 000-037752 (the Contract Notice).",
        "hasOptions": true,
        "id": "3",
        "options": {
          "description": "The duration of the Framework Agreement is 5 years, but extendable up to 10 years (in aggregate) at SPT\u0027s option. The duration of call-off contracts for specific packages may extend beyond the end of the overarching Framework Agreement."
        },
        "status": "cancelled",
        "title": "Design \u0026 Construction of 132kV Overhead Line Works"
      }
    ],
    "mainProcurementCategory": "works",
    "procurementMethod": "selective",
    "procurementMethodDetails": "Negotiated procedure with prior call for competition",
    "reviewDetails": "Any proceedings relating to a breach of a duty owed by SPT to an economic operator under the Utilities Contracts (Scotland) Regulations 2016 in relation to this procurement must be started within 30 days beginning with the date when the economic operator first knew or ought to have known that grounds for starting the proceedings had arisen unless the court considers that there is a good reason for extending the period within which proceedings may be brought, in which case the court may extend that period up to a maximum of 3 months from that date.",
    "status": "complete",
    "techniques": {
      "hasFrameworkAgreement": true
    },
    "title": "SPT - Strategic Agreement for Transmission Overhead Line Works"
  }
}