The purpose of these works is to prevent the Nant y Bai watercourse from continuing to scour (causing active erosion of) spoil heaps that make up its banks and causing mobilisation of metal-rich spoil into the watercourse. It is proposed to install a mixture of scour protection interventions including rock filled rolls and bags, geotextile matting and wooden stakes at a number of discrete areas along the bank to stabilise the spoil and prevent ongoing erosion by the Nant y Bai. We would welcome input from the Contractor regarding current design methodology based on previous experiences. The Works comprise the following: • Install scour protection measures in accordance with the drawings; • Install slope stabilisation measures in accordance with the drawings; • Supply and install 150No. rock filled bags as specified on the drawings and as directed on site to provide scour protection in Areas 3, 5 and 6; • Translocate Purple Moor grass into the working area in accordance with the drawings. The source of Purple Moor grass to be agreed with the ecological supervisor but shall be within the Site; • Install silt traps in accordance with the drawings; • Install an overland pipe with associated capture structure and outfall structure in accordance with the drawings; • Deliver plant and materials along designated routes to limit impact on the protected ecology and provide any equipment necessary to minimize the impact on the designated routes. This may include helicopters to aid in load lifting and placement of rock roll bags; and • Plan and execute temporary flow diversion measures to enable the Works in the river bed to be completed. The Works must be carried out, including transportation of plant and materials, in a way that: • Does not cause undue harm to the local ecology, including plants, trees and particularly the protected Calaminarian habitats (comprising metallophyte flowering and non-flowering plant species); • Does not damage local heritage features, including historic mining structures and artefacts; • Does not cause undue disruption to the local community; • Does not cause damage to existing services; • Does not cause damage to the forest track road, • Is in accordance with the relevant Environmental Action Plan (EAP) as prepared by the Mining Remediation Authority and agreed with NRW.
No linked documents found for this notice.
Lot 1 Status: complete
Award Title: Nant Y Mwyn Scour Protection Works
{
"awards": [
{
"aboveThreshold": false,
"contractPeriod": {
"endDate": "2026-05-29T23:59:59+01:00",
"maxExtentDate": "2026-09-01T23:59:59+01:00",
"startDate": "2026-02-16T00:00:00Z"
},
"date": "2026-01-29T00:00:00Z",
"documents": [
{
"datePublished": "2026-01-30T11:40:09Z",
"description": "Contract award notice on Find a Tender",
"documentType": "awardNotice",
"format": "text/html",
"id": "008381-2026",
"noticeType": "UK6",
"url": "https://www.find-tender.service.gov.uk/Notice/008381-2026"
}
],
"hasRenewal": true,
"id": "1",
"items": [
{
"additionalClassifications": [
{
"description": "Excavation work at archaeological sites",
"id": "45112450",
"scheme": "CPV"
}
],
"deliveryAddresses": [
{
"country": "GB",
"countryName": "United Kingdom",
"region": "UKL"
}
],
"id": "1",
"relatedLot": "1"
}
],
"mainProcurementCategory": "works",
"milestones": [
{
"dueDate": "2026-02-11T23:59:59Z",
"id": "1",
"status": "scheduled",
"type": "futureSignatureDate"
}
],
"relatedLots": [
"1"
],
"renewal": {
"description": "An extension may be required due to adverse weather conditions in the area or other conditions on site which prevent a timely delivery of works."
},
"status": "active",
"suppliers": [
{
"id": "GB-COH-04886688",
"name": "SANCTUS LIMITED"
}
],
"title": "Nant Y Mwyn Scour Protection Works",
"value": {
"amount": 151415.73,
"amountGross": 181698.88,
"currency": "GBP"
}
}
],
"bids": {
"statistics": [
{
"id": "1",
"measure": "bids",
"relatedLot": "1",
"value": 8
},
{
"id": "2",
"measure": "finalStageBids",
"relatedLot": "1",
"value": 8
},
{
"id": "3",
"measure": "smeFinalStageBids",
"relatedLot": "1",
"value": 8
},
{
"id": "4",
"measure": "vcseFinalStageBids",
"relatedLot": "1",
"value": 0
}
]
},
"buyer": {
"id": "GB-PPON-PRPD-5825-QDVY",
"name": "Mining Remediation Authority"
},
"date": "2026-01-30T11:40:09Z",
"id": "008381-2026",
"initiationType": "tender",
"language": "en",
"ocid": "ocds-h6vhtk-058ec4",
"parties": [
{
"address": {
"country": "GB",
"countryName": "United Kingdom",
"locality": "Nottinghamshire",
"postalCode": "NG18 4RG",
"region": "UKF15",
"streetAddress": "200 Lichfield Lane"
},
"contactPoint": {
"email": "natalie.earnshaw@miningremediation.gov.uk",
"name": "Natalie Earnshaw"
},
"details": {
"classifications": [
{
"description": "Public authority - central government",
"id": "publicAuthorityCentralGovernment",
"scheme": "UK_CA_TYPE"
}
]
},
"id": "GB-PPON-PRPD-5825-QDVY",
"identifier": {
"id": "PRPD-5825-QDVY",
"scheme": "GB-PPON"
},
"name": "Mining Remediation Authority",
"roles": [
"buyer"
]
},
{
"additionalIdentifiers": [
{
"id": "PPRW-4732-YNBJ",
"scheme": "GB-PPON"
}
],
"address": {
"country": "GB",
"countryName": "United Kingdom",
"locality": "Gloucester",
"postalCode": "GL2 4DH",
"region": "UKK13",
"streetAddress": "Sanctus House 1 Olympus Park Business Centre"
},
"contactPoint": {
"email": "info@sanctusltd.co.uk"
},
"details": {
"scale": "sme",
"url": "http://www.sanctusltd.com",
"vcse": false
},
"id": "GB-COH-04886688",
"identifier": {
"id": "04886688",
"scheme": "GB-COH"
},
"name": "SANCTUS LIMITED",
"roles": [
"supplier"
]
}
],
"tag": [
"award",
"contract"
],
"tender": {
"description": "The purpose of these works is to prevent the Nant y Bai watercourse from continuing to scour (causing active erosion of) spoil heaps that make up its banks and causing mobilisation of metal-rich spoil into the watercourse. It is proposed to install a mixture of scour protection interventions including rock filled rolls and bags, geotextile matting and wooden stakes at a number of discrete areas along the bank to stabilise the spoil and prevent ongoing erosion by the Nant y Bai. We would welcome input from the Contractor regarding current design methodology based on previous experiences.\nThe Works comprise the following:\n\u2022 Install scour protection measures in accordance with the drawings;\n\u2022 Install slope stabilisation measures in accordance with the drawings;\n\u2022 Supply and install 150No. rock filled bags as specified on the drawings and as directed on site to provide scour protection in Areas 3, 5 and 6;\n\u2022 Translocate Purple Moor grass into the working area in accordance with the drawings. The source of Purple Moor grass to be agreed with the ecological supervisor but shall be within the Site;\n\u2022 Install silt traps in accordance with the drawings;\n\u2022 Install an overland pipe with associated capture structure and outfall structure in accordance with the drawings;\n\u2022 Deliver plant and materials along designated routes to limit impact on the protected ecology and provide any equipment necessary to minimize the impact on the designated routes. This may include helicopters to aid in load lifting and placement of rock roll bags; and\n\u2022 Plan and execute temporary flow diversion measures to enable the Works in the river bed to be completed.\nThe Works must be carried out, including transportation of plant and materials, in a way that:\n\u2022 Does not cause undue harm to the local ecology, including plants, trees and particularly the protected Calaminarian habitats (comprising metallophyte flowering and non-flowering plant species);\n\u2022 Does not damage local heritage features, including historic mining structures and artefacts;\n\u2022 Does not cause undue disruption to the local community;\n\u2022 Does not cause damage to existing services;\n\u2022 Does not cause damage to the forest track road,\n\u2022 Is in accordance with the relevant Environmental Action Plan (EAP) as prepared by the Mining Remediation Authority and agreed with NRW.",
"id": "CA18/2/1/127",
"legalBasis": {
"id": "2023/54",
"scheme": "UKPGA",
"uri": "https://www.legislation.gov.uk/ukpga/2023/54/contents"
},
"lots": [
{
"id": "1",
"status": "complete"
}
],
"procurementMethod": "open",
"procurementMethodDetails": "Below threshold - open competition",
"status": "complete",
"title": "Nant y Mwyn 25-26 Scour Protection Works"
}
}