Opportunities
Showing page 1 of 1 (8 results)
in all-time data.
Sector: Construction work
Description: Quayside Civils (These works are the focus of this PQQ)
- Setting up principal contractor welfare area including all temporary service connections,
- Breaking out and disposal of concrete guide walls following installation by quay wall contractor,
- Removal of piling mat, installed by Others,
- Cropping of diaphragm wa...
Status: n/a
Deadline: n/a
Contract Start: n/a
Published: 13 Jan 2026, 12:01
Sector: Construction work
Description: These works are the focus of this PQQ.
Proposed development of the yard area to a varying finished ground level to suit the drainage design and to tie into that of Phase 1, including removal of existing trees and raising of the land using existing material on site while achieving a load bearing capacity of 250kPat/m2.
...
Status: n/a
Deadline: n/a
Contract Start: n/a
Published: 13 Jan 2026, 12:00
Sector: works
Description: Quayside Civils (These works are the focus of this PQQ)
- Setting up principal contractor welfare area including all temporary service connections,
- Breaking out and disposal of concrete guide walls following installation by quay wall contractor,
- Removal of piling mat, installed by Others,
- Cropping of diap...
Status: n/a
Deadline: n/a
Contract Start: n/a
Published: 13 Jan 2026, 00:00
Sector: works
Description: These works are the focus of this PQQ.
Proposed development of the yard area to a varying finished ground level to suit the drainage design and to tie into that of Phase 1, including removal of existing trees and raising of the land using existing material on site while achieving a load bearing capacity of 250kPat/m2...
Status: n/a
Deadline: n/a
Contract Start: n/a
Published: 13 Jan 2026, 00:00
Sector: Construction work
Description: These works are the focus of this PQQ.
Proposed development of the yard area to a varying finished ground level to suit the drainage design and to tie into that of Phase 1, including removal of existing trees and raising of the land using existing material on site while achieving a load bearing capacity of 250kPat/m2.
...
Status: active
Amount: £10,000,000
Deadline: 16 Jan 2026, 12:00
Contract Start: n/a
Published: 04 Dec 2025, 15:50
Sector: works
Description: These works are the focus of this PQQ.
Proposed development of the yard area to a varying finished ground level to suit the drainage design and to tie into that of Phase 1, including removal of existing trees and raising of the land using existing material on site while achieving a load bearing capacity of 250kPat/m2...
Status: active
Amount: £10,000,000
Deadline: 16 Jan 2026, 12:00
Contract Start: n/a
Published: 04 Dec 2025, 00:00
Sector: Construction work
Description: Quayside Civils (These works are the focus of this PQQ)
- Setting up principal contractor welfare area including all temporary service connections,
- Breaking out and disposal of concrete guide walls following installation by quay wall contractor,
- Removal of piling mat, installed by Others,
- Cropping of diaphragm wa...
Status: active
Amount: £23,000,000
Deadline: 16 Jan 2026, 12:00
Contract Start: n/a
Published: 03 Dec 2025, 17:00
Sector: works
Description: Quayside Civils (These works are the focus of this PQQ)
- Setting up principal contractor welfare area including all temporary service connections,
- Breaking out and disposal of concrete guide walls following installation by quay wall contractor,
- Removal of piling mat, installed by Others,
- Cropping of diap...
Status: active
Amount: £23,000,000
Deadline: 16 Jan 2026, 12:00
Contract Start: n/a
Published: 03 Dec 2025, 00:00